Interview Prep/SRE & Reliability/SLO Design & Error Budget Decisions

Your SLO window is 30 days rolling, and a 3-hour outage happened 25 days ago. The team asks why the freeze is still on.

BeginnerScenarioSLO Design & Error Budget Decisions
Answer

Situation read → In a rolling window, the outage counts until it ages out, 30 days after it happened.

What I'd do →

  1. Show the burn-down chart: budget is still negative because the outage is inside the window.
  2. Calculate when it ages out (5 more days) and what the SLI will be after that.
  3. Check whether the policy allows lifting the freeze early when the action items are done; many policies do.
  4. Use the remaining days to finish the postmortem action items.

Why → Rolling windows deliberately make big incidents have lasting consequences, which drives the fixes.

Interview tip → Explain rolling vs calendar windows with this exact example.