Convert 99.95% monthly availability into allowed downtime per week and per day.
IntermediateConceptAvailability Math
Answer
per week: 7 x 24 x 60 = 10,080 min x 0.0005 = 5.04 minutes
per day: 1,440 min x 0.0005 = 0.72 minutes ≈ 43 seconds
Useful sanity check: a single 10-minute deploy outage per week already breaks 99.95%.
More on Availability Math
How much downtime per month does each "nine" allow?BeginnerHow do you calculate composite availability of services in series?BeginnerHow do you calculate availability of redundant components in parallel?BeginnerWhy do the parallel-availability numbers lie in practice?AdvancedYour service depends on five services each at 99.9%. What availability can you promise?IntermediateWhat is the difference between a hard and a soft dependency?Intermediate