How long did the project take, and how was the work planned?
BeginnerBehavioralWalking through your project
Answer
Good answer looks like → "About 4 months. We broke it into milestones: month 1 infrastructure with Terraform, month 2 CI pipelines and the first service on EKS, months 3–4 migrating the remaining services in waves. We tracked tasks in Jira in 2-week sprints with a demo at the end of each milestone."
Follow-ups to expect → What slipped? What did you cut from scope? Who decided the migration order?
Red flags → No sense of timeline or phases.
More on Walking through your project
Walk me through the most important project on your resume.BeginnerWhat problem was this project solving for the business?BeginnerDraw the architecture of your project.IntermediateWhat exactly was your role versus your team's?BeginnerHow many services, environments and users did this project support?BeginnerWhy did you choose this tech stack?Intermediate