Management wants a change approval board after a bad outage. How do you introduce change management without slowing everyone down?

IntermediateScenarioTeam and process
Answer

Situation read → Weekly approval boards create big, batched, riskier changes. Offer controls that address the real cause of the outage and are automated.

What I'd do →

  1. Look at what caused the outage: missing tests, no canary, a risky change type (DB, network)?
  2. Classify changes by risk:
    • Standard (app deploys through the pipeline with tests and canary): pre-approved, no meeting.
    • Normal (infra, network, schema): peer review plus a plan in the PR, scheduled in a window.
    • Emergency: break-glass with a review afterwards.
  3. Put the controls in the pipeline: required reviewers, automated checks, deploy freezes for peak periods.
  4. Measure change failure rate before and after to show it's working.

Why → Risk-based, automated controls reduce failures without the delay of a weekly board.

Interview tip → Cite DORA findings that heavyweight approval boards don't reduce failure rates.