The error budget for the month is exhausted on day 18. What happens now?

IntermediateScenarioSLOs and Error Budgets
Answer

Situation read → The error budget policy should already define this; if it does not, write it now.

What I'd do →

  1. Freeze risky feature launches for that service; allow fixes and reliability work.
  2. Run a review of what burned the budget (top incidents, bad deploys, dependencies).
  3. Prioritise the top reliability actions in the next sprint.
  4. Lift the freeze when the rolling window recovers or when the fixes ship, as agreed.
  5. Report to stakeholders with data.

Why → The budget turns reliability versus velocity into a data-driven decision, not an argument.

Interview tip → Mention that the policy must be signed by product leadership, or it will be ignored.