A blue-green release looks fine in preview, but after switching, latency spikes. How do you design protection for this?

IntermediateScenarioCI Integration & Progressive Delivery
Answer

Situation read → Preview traffic was not representative.

What I'd do →

  1. Add postPromotionAnalysis with latency and error metrics; failure switches the active Service back.
  2. Keep scaleDownDelaySeconds long enough (for example 10 minutes) that the old ReplicaSet is still up for instant rollback.
  3. Use prePromotionAnalysis with synthetic load against the preview Service.
  4. Consider canary instead, so real traffic ramps gradually.

Why → Blue-green is all-or-nothing on cutover; post-promotion checks plus a warm old version make it reversible.

Interview tip → Explain why canary is safer when realistic traffic cannot be simulated.